(our part starts at 13m52s)
Slides are here.
The plan boils down to two things:
- We will use burndown charts to track progress over the course of the release.
- We will be building a bit more agility into our schedule by working in three separate milestones. These are simply overlaid on top of the normal Ubuntu schedule.
The milestones look like this:
Goal | Milestone | Date |
---|---|---|
Initial Integration and Risky Work | Alpha 2 | 2010-01-14 |
Development | Alpha 3 | 2010-02-25 |
Clean Up and Completion | Beta 2 | 2010-04-08 |
The Lucid Lynx Release Schedule is not effected by this plan,
The desktop team kept a burndown chart for Karmic, and it worked quite well.
No comments:
Post a Comment